Monthly Archives: April 2011

We’ve Been Framed

Whew!  This was seriously busy week for all involved on our house.  Last time we spoke, there was a giant hole in the house.  We returned Monday for our weekly on-site status meeting with our architect and project manager to … Continue reading

Posted in Building | 1 Comment

It Just Keeps Coming

We ran some errands today in Southeast and went past the house to see what was happening. As I mentioned, the framing crew was planning on working through the weekend to be ready to take the roof off next week … Continue reading

Posted in Uncategorized | Leave a comment

OMG

As promised, this week was a big week.  M went over to the house yesterday to check up on things and holy batshit! there was a lot going on. M called me at work to give me an update.  The … Continue reading

Posted in Building, Demolition | 2 Comments

Weekend Update

Looks like the concrete forms are in place and ready to pour on Monday. And we bought all the shower parts.  We went with temperature and volume control on the shower valve, and a diverter instead of two shower valves. … Continue reading

Posted in Bathroom, Building | 1 Comment

And We’re Off!

After a delay while everyone sorted out what to do about the foundation, work has begun!  Today, the excavators did some trench digging and will start pouring concrete probably Monday.  It needs to go on in batches, so they don’t … Continue reading

Posted in Bathroom, Demolition, Uncategorized | 1 Comment